Pembangunan Simpang Temu Lebak Lubus Capai 68 Persen
....
photo Budhi Firmansyah Surapati - Beritajakarta.id

Lebak Bulus Intersection Construction Has Reached 68 Percent

PT MRT Jakarta (Perseroda) speeds up the Lebak Bulus Intersection construction work on Jalan RA Kartini, South Jakarta. As of mid-May 2022, the overall construction progress has reached 68 percent.

It is targeted to be completed in August 2022

PT MRT Jakarta (Perseroda) President Director William P. Sabandar conveyed that the infrastructure development of the Lebak Bulus Intersection was divided into two parts, namely the Transit Plaza in front of the Poins Square Lebak Bulus and the Interconnection Bridge as long as 200 meters that connect the Lebak Bulus Grab MRT Station to the Transit Plaza.

"This development project is carried out by PT Inti Menara Jaya (Poins Square)," he added, Wednesday (5/25).

MRT Jakarta: Most Passengers Seen in May 2020 Amid Covid-19

He stated that the development project had been declared by the Jakarta Governor Anies Baswedan on December 8, 2021. The Simpang Temu has supporting facilities in form of bicycle parking, kiss & ride (drop-off area), Transjakarta stops, and online transportation stops in a 2,000 square meters park area.

In general, the stages of development were divided into five sections, namely planning, funding, licensing, construction, and assets handover. Currently, it has entered the construction phase and the next is preparing BAST.

"It is targeted to be completed in August 2022. We are quite optimistic that it can be realized," he said.

Linked News
Popular News indeks
  1. Transjakarta Wins Popular Company Award in Land Transportation Sector

    access_time04-09-2024 remove_red_eye1004 personAldi Geri Lumban Tobing
  2. PPKUKM Agency Encourages Digital Transaction for Fostered MSMEs

    access_time04-09-2024 remove_red_eye904 personFolmer
  3. Transportation Agency Urges Mass Participants to Use Public Transportation

    access_time03-09-2024 remove_red_eye851 personAldi Geri Lumban Tobing
  4. Jakarta LRT Phase 1B Construction Achieves Positive Deviation of 26.64 Percent

    access_time06-09-2024 remove_red_eye847 personAldi Geri Lumban Tobing
  5. Transjakarta Prepares Parking Area and Additional Fleet for Grand Mass

    access_time05-09-2024 remove_red_eye761 personAldi Geri Lumban Tobing